WHO | Master Planned Community in Fort Bend County, Texas |
CHALLENGE | Customer was in need of a wastewater treatment plant designed to expand with the community, rather than building a 600,000 gallons per day plant. |
SOLUTION | AUC provided a three phase solution that reduced necessary upfront capital. Each phase would install a 200,000 GPD, leased wastewater treatment plant, scheduled to increase with capacity demands. |
Phased Growth Case Study
Industrial Case Study
WHO | Major HVAC Manufacturer |
CHALLENGE | Needed a wastewater treatment plant to serve its new manufacturing hub in a remote area |
SOLUTION | AUC provided a 150,000 GPD wastewater treatment plant |
Lease Case Study - Capital Restrictions
WHO | Master Planned Community, Harris County, Texas |
CHALLENGE | Treat wastewater generated by an 11,400-acre planned community in a growth phase |
SOLUTION | Install and lease a 0.6 MGD treatment plant allowing the community to spread capital costs over several years and match capacity with short term needs |
PERMANENT TREATMENT PLANT COST | $8 million |
LEASE ALTERNATIVE | AUC provided a 5-year lease costing the developer a total investment of less than $2 million. |
Bypass Case Study – Temporary Plants
WHO | Municipal Utility District, Harris County, Texas |
CHALLENGE | Treating flow during emergency plant repair |
SOLUTION | Within 30 days AUC Group provided a temporary 0.4MGD wastewater treatment plant to treat existing flow |