Phased Growth Case Study
CUSTOMER | A master-planned community in Fort Bend, Texas. |
CHALLENGE | The client needed a wastewater treatment plant designed to expand in steps with the community rather than a large-capacity plant at the outset of the project. |
SOLUTION | AUC provided a three-phase solution that reduced necessary upfront capital, with each phase including installation of a 200,000 GPD leased wastewater treatment plant for a total capacity of 600,000 GPD. |